Construction Loan Draw Calculator
Estimate the interest a construction loan will charge before completion, from up to three draws, the months each is outstanding and the annual rate.
Construction Loan Draw Calculator
Background.
A construction loan is not handed over in one lump. The lender releases money in draws as the work reaches agreed stages, typically after an inspector confirms that the foundation is poured or the frame is up, and interest runs only on what has actually been disbursed. During the build most borrowers pay that interest monthly and nothing toward principal, either out of pocket or from an interest reserve, a line in the loan budget that pays the interest from the loan itself.
Sizing that reserve, or your own cash cushion, means adding up interest on a balance that grows in steps. Each draw costs its amount times the rate times the fraction of a year it is outstanding, and the totals simply add. On the default schedule, $100,000 out for nine months, $80,000 for six and $50,000 for three at 8%, the interest comes to $10,200. Had the whole $230,000 been advanced on day one for nine months, it would be $13,800, which is why staged funding matters to the budget.
The estimate is as good as the schedule behind it, and schedules slip. Every extra month the full $230,000 stays on the construction loan before conversion or payoff costs another $1,533.33 at 8%, and a weather delay or a late inspection pushes every draw back together. Build some of that slack into the months you enter. A lender's own figure can also differ because it counts actual days, may accrue on a 360-day year, may adjust a floating rate during the build, and charges interest on interest paid from the reserve.
What is construction loan draw calculator?
A construction loan draw is a single disbursement under a construction loan's total commitment, released against completed work and usually after an inspection; the schedule of draws is set out in the loan agreement, sometimes with retainage held back until the job is finished. The interest reserve is the amount budgeted to pay interest on the disbursed balance until the loan converts to permanent financing or is repaid. Here it is estimated as simple interest on each draw for the months it is outstanding, which also gives the dollar-weighted average time the money is out.
How to use this calculator.
- Enter the First draw, Second draw and Third draw amounts from the draw schedule in your construction budget or loan agreement. If a stage will not need a draw, enter 0.
- For each draw, enter the months it will be outstanding: from the expected date of that draw to the date the construction loan converts to permanent financing or is paid off, not to the end of the build.
- If your schedule has more than three draws, either group draws that fall close together, or run the calculator twice with different draws and add the two interest figures, since each draw's interest is independent.
- Enter the Annual interest rate on the construction loan. For a floating rate, use your best estimate of the average over the build, and try a rate a point higher to see what a rise would cost.
The formula.
Interest reserve = Σ (Dᵢ × r × mᵢ ÷ 12), where Dᵢ is each draw, mᵢ the months it is outstanding and r the annual rate as a decimal. Because the rate is the same for every draw, this collapses to r ÷ 12 times the dollar-months: the sum of each draw multiplied by its months. Dividing dollar-months by the total drawn gives the weighted outstanding months, the average time a borrowed dollar is out, so the reserve also equals total drawn × r × weighted months ÷ 12.
The model is simple interest on fixed balances. It does not add each month's interest to the balance, which is what happens when the interest reserve itself is a funded line in the loan: on the default schedule that compounding adds about $223 over nine months. It counts whole months rather than days, ignores fees, inspection charges and title updates on each draw, and holds the rate constant. The two inputs that move the answer most are the months on the largest draws and the date the construction phase ends.
A worked example.
A builder's schedule calls for $100,000 at the start, $80,000 three months in and $50,000 at month six, with the loan converting to a permanent mortgage at month nine. That leaves the draws outstanding for 9, 6 and 3 months at an 8% rate. Dollar-months: $100,000 × 9 = $900,000, $80,000 × 6 = $480,000 and $50,000 × 3 = $150,000, for $1,530,000 in total. Monthly rate: 8% ÷ 12. Interest: $1,530,000 × 0.08 ÷ 12 = $10,200, the interest reserve. The total drawn is $230,000, and $1,530,000 ÷ $230,000 gives a weighted outstanding time of about 6.65 months. Spread over the nine months of the build, the balance averages $1,530,000 ÷ 9 = $170,000, about 74% of the money eventually borrowed, and $10,200 is simply 8% a year on that average balance for three quarters of a year.
Frequently asked questions.
How big should the interest reserve in my construction budget be?
Why does my lender's interest figure come out a little higher?
Do I make payments on the construction loan while the house is being built?
What happens to the interest when the construction loan converts to a mortgage?
Can I enter more than three draws?
Why do the weighted outstanding months matter?
References& sources.
How this page was produced
- Published by
- Quanta Calculator
- Overseen by
- Daniel, Quanta Calculator Researcher
- Primary sources
- 3 cited below
- Method
- interest reserve = Σ(draw amount × annual rate × months outstanding ÷ 12)
- Published
- Last verified
Built with AI assistance and verified by automated tests against the cited sources — every worked example on this page is computed by the same code that runs the calculator. How we build and check calculators.
In this category
Embed
Quanta Pro
Paid features are coming later.
- All 1560 calculators remain free
- No billing is enabled