Audited 05 Aug 2026·Last updated 28 Oct 2026·3 citations·Tier 2·0 uses

Stone Calculator

Work out how many tonnes of crushed stone or gravel to order from length, width, finished depth, loose bulk density and a compaction allowance.

Stone Calculator

m
m
m
kg/m³
%
Estimated order mass
3.1104
Mass of loose stone to order in metric tonnes (1,000 kg), with the allowance included.
Order volume
1.944m³
Compacted geometric volume
1.8m³

Background.

Stone is sold by weight but laid by volume, and most ordering mistakes happen in the conversion. The quarry weighs the lorry; you measure a parking pad or a path base with a tape. Getting from one to the other needs two facts a tape cannot give you: how much a cubic metre of that particular stone weighs as it sits in the heap, and how much extra loose stone it takes to reach a finished thickness once the layer has been compacted.

The first is bulk density, and it is not the density of rock. Solid granite weighs roughly 2,700 kg per cubic metre, but a heap of crushed pieces is partly air, so a cubic metre in the truck weighs far less. How much less depends on grading — a clean single-size stone leaves bigger gaps than a graded mix whose fines fill them — and on moisture, because a wet load carries water in those gaps. The 1,600 kg/m³ default is a starting value, not a property of any named product; the yard can usually give you the figure for what it sells.

The second is the allowance. A base that must finish 100 mm thick needs more than 100 mm of loose stone spread on it, and some always ends up pressed into soft ground, spilled at the edges or left behind on the drive. One percentage covers all of it, added on top of the finished volume.

After that the arithmetic is short: length × width × finished depth, scaled up by the allowance, multiplied by bulk density. Volume and weight are both shown, so a quote priced either way can be checked. What the page cannot know is how your supplier sells — minimum loads, bag sizes, or whether their ton is a metric tonne.

What is stone calculator?

The order mass is the weight of loose stone to ask a supplier for so that, once spread and compacted, it fills a rectangular area to a chosen finished depth. It rests on three quantities: the compacted geometric volume (the space being filled), the order volume (that space enlarged by the waste and compaction allowance), and the loose bulk density — the mass of one cubic metre of stone including the air between the pieces, the property ASTM C29/C29M describes how to measure. The result is in metric tonnes of 1,000 kg.

How to use this calculator.

  1. Tape the length and width of the bay, path or pad in metres. For an L-shaped or irregular area, split it into rectangles, run each one separately and add the tonnages.
  2. Enter the compacted depth: the thickness the layer must have after rolling or plate compaction, not the loose depth you spread. 100 mm is 0.1 m; 75 mm is 0.075 m.
  3. Replace the 1,600 kg/m³ default with the supplier's loose bulk density for the exact product if you can get it, and ask whether it was measured dry or as delivered.
  4. Set the waste / compaction allowance. A soft subgrade, ragged edges or heavy compaction call for more; 0% gives the bare geometric quantity with no margin at all.
  5. Compare the tonnes or the order volume with how the yard sells — by the tonne, by the bag or by the cubic metre — and round up to whole loads or bags.

The formula.

Order mass = L×W×D × (1+waste%) × bulk density

Order mass (t) = L × W × D × (1 + a/100) × ρ ÷ 1,000. L, W and D are length, width and finished compacted depth in metres, so their product is the compacted volume in cubic metres. The allowance a, in percent, enlarges that to the loose volume to order; 8% turns 1.8 m³ into 1.944 m³. Multiplying by ρ, the loose bulk density in kg/m³, gives kilograms, and the division by 1,000 gives metric tonnes. Every term enters as a straight multiplier, so a 10% error in depth or density becomes a 10% error in the order. Depth is the one people get wrong most easily: a base specified at 150 mm rather than 100 mm needs half as much stone again. Keep the density at its loose value. The allowance is what accounts for the stone settling tighter under compaction, so entering a higher compacted density as well would count that settlement twice.

A worked example.

Example

Take a base for a parking bay 6 m long and 3 m wide that must finish 0.1 m (100 mm) thick after compaction, using stone at 1,600 kg/m³ with an 8% allowance. Multiplying out the footprint and finished depth, 6 × 3 × 0.1 gives 1.8 m³ of compacted stone. The allowance raises it to 1.8 × 1.08 = 1.944 m³ of loose stone to order. At 1,600 kg per cubic metre that weighs 1.944 × 1,600 = 3,110.4 kg, which is 3.1104 tonnes. Without any allowance the same bay would come to 2.88 t, so the 8% adds about 230 kg. A wrong density matters more: if the yard's stone is actually 1,800 kg/m³, the same 1.944 m³ weighs 3.4992 t, and an order of 3.1104 t placed at the default figure would arrive about 11% short in volume.

depth0.1
bulk Density1,600
length6
waste Percent8
width3

Frequently asked questions.

How many tonnes of crushed stone fill one cubic metre?
It depends on the stone and its grading, which is why bulk density is an input rather than a fixed value. A heap of crushed stone is part air, so a cubic metre weighs well under the roughly 2,700 kg of solid granite. The 1,600 kg/m³ default is a placeholder; a supplier's figure for the exact product beats any generic number.
My supplier quotes in tons. Are those the tonnes shown here?
Not necessarily. The page reports metric tonnes of 1,000 kg. A US short ton is 907.18 kg, so the example's 3.1104 tonnes is about 3.43 short tons. If the quote does not say which ton it means, ask before comparing prices, because the difference is close to 10%.
What allowance should I enter for compaction and waste?
There is no universal figure. The allowance must cover stone that packs tighter than it was delivered, stone pushed into soft ground and spillage at the edges. If the supplier quotes a compaction factor, convert it: a factor of 1.2 means loose volume is 1.2 times compacted volume, so enter 20, then add a little for handling.
Should the depth be measured before or after compacting?
After. The depth field is the finished thickness the job calls for, and the allowance accounts for the extra loose stone needed to reach it. Entering a loose depth and an allowance as well would count compaction twice and over-order, sometimes by a whole extra load on a large area.
Can I order by volume instead of by weight?
Yes. The order volume is the loose quantity to ask for, 1.944 m³ in the default example. Yards that sell by the cubic yard need it converted: one cubic metre is about 1.308 cubic yards, so the example comes to roughly 2.54 yd³ of loose stone.
Why might a wet load cover less ground than the estimate?
Water sits in the gaps between the stones and adds weight without adding volume. If the density you entered was measured on dry stone and the load arrives soaked, the tonnage on the ticket buys fewer cubic metres than the estimate assumes. When buying by weight, ask whether the quoted density is for the material as delivered.

How this page was produced

Published by
Quanta Calculator
Primary sources
3 cited below
Method
Order mass = L×W×D × (1+waste%) × bulk density
Published
Last verified

Built with AI assistance and verified by automated tests against the cited sources — every worked example on this page is computed by the same code that runs the calculator. How we build and check calculators.

In this category

Embed

Quanta Pro

Paid features are coming later.

  • All 1560 calculators remain free
  • No billing is enabled
Coming soon