Audited ·Last updated 27 Jul 2026·7 citations·Tier 1·0 uses

Concrete Volume Calculator

Free concrete calculator. Get cubic yards, bag counts, and cost for slabs, columns, and footings — with the standard 10% waste factor included.

Concrete Volume Calculator

Shape
Unit
Long dimension of the slab or footing. Ignored for columns.
Short dimension of the slab or footing. Ignored for columns.
Slab/footing thickness or column height in the chosen unit. 4 inches ≈ 0.333 ft.
Diameter is always entered in inches. Only used for columns.
in
Extra concrete to cover spillage, uneven subgrade, and over-excavation. 10% is the contractor standard.
%
Typical 2025 U.S. ready-mix price runs $140–$180 per cubic yard delivered.
$
Cubic Yards Required
1.3567
Total ready-mix concrete to order, including waste factor.
Cubic Feet
36.63 ft³
Cubic Meters
1.0372 m³
60 lb Bags Needed
82 bags
80 lb Bags Needed
62 bags
Estimated Material Cost
$203.50

Background.

This concrete calculator turns a few simple measurements — length, width, thickness, or column diameter — into the exact volume of concrete you need to pour a slab, set a column, or cast a footing. It returns the answer in cubic yards (how ready-mix is sold in the United States), cubic feet, and cubic meters, then converts that volume into the number of 60-pound and 80-pound pre-mix bags required if you are buying from a home center instead of ordering a truck. It also estimates the material cost based on the price per cubic yard you enter. The calculator applies a 10% waste factor by default, which you can adjust between 0 and 20 percent depending on how rough your subgrade is and how confident you are in your formwork.

Concrete volume math is unforgiving in two directions. Under-order, and you end up scrambling for a few extra bags while a slab starts to set — leaving a cold joint that becomes a permanent crack. Over-order by too much, and you pay a short-load fee, or you waste a quarter-yard of material that has nowhere to go once the truck arrives. The geometry behind each shape is straightforward. A slab or footing is a rectangular prism: length times width times thickness. A column is a cylinder: pi times the radius squared, times the height. The trick is that no single dimension is usually given in the same unit. Slabs are described in feet, thicknesses in inches, columns in inches of diameter and feet of height, and the final answer is sold in cubic yards. One cubic yard equals 27 cubic feet, and a 4-inch slab is one-third of a foot thick, so a 10-foot by 10-foot patio at 4 inches comes out to 100 × (4/12) = 33.33 cubic feet, which is 1.23 cubic yards before waste — 1.36 yards once you add the standard 10% cushion.

That cushion is not optional in real construction. The Portland Cement Association and the National Ready Mixed Concrete Association both flag that a perfectly screeded subgrade is rare; over-excavation, settled gravel base, spillage out of the chute, and concrete that hardens in the truck on a hot day all eat into your usable volume. The 10% number is what working concrete finishers use in the field, and most ready-mix dispatchers will quietly round your order up anyway. If your subgrade is uneven or you are pouring into deep footing trenches, push the waste factor to 15%.

Bagged concrete is sold by dry weight, not finished volume, so the conversion is the second place beginners get tripped up. An 80-pound bag of Quikrete or Sakrete yields about 0.60 cubic feet of cured concrete; a 60-pound bag yields about 0.45 cubic feet. That means roughly 60 of the 80-pound bags or 80 of the 60-pound bags fill one cubic yard. Anything more than about half a yard — roughly 30 of the 80-pound bags — and you are working too hard for too little concrete: order ready-mix instead. A standard concrete truck holds about 10 cubic yards, but most suppliers will deliver as little as one yard with a short-load fee of $50–$150. Below one yard, bags win on price and convenience. Above that, the truck wins on price, consistency, and your back.

This calculator does not size rebar, mesh, or fiber reinforcement, and it does not specify the mix design. For most homeowner work — patios, walks, shed pads — a 3,000 PSI mix is standard; driveways and footings exposed to freeze-thaw typically call for 4,000 PSI with air entrainment per ACI 318. Whatever mix you order, the volume math here is the same.

What is concrete volume calculator?

A concrete volume calculator computes the cubic volume of fresh concrete needed to fill a defined shape — most commonly a rectangular slab, a cylindrical column, or a strip or pad footing — and converts that volume into the purchase units the supplier uses. In the United States ready-mix is sold by the cubic yard, dry-mix bags are sold by weight (typically 60 lb or 80 lb), and metric suppliers and most international markets work in cubic meters. The calculator also bakes in a waste factor to account for spillage, subgrade variation, and over-excavation, which is standard practice on every commercial pour.

How to use this calculator.

  1. Choose the shape — slab, column, or footing — that matches what you are pouring.
  2. Pick the unit (feet or meters) for your length, width, and thickness measurements.
  3. Enter length and width for a slab or footing. For a column, leave these and enter the column diameter (in inches) and the column height as the thickness field.
  4. Enter the slab or footing thickness. Remember that 4 inches is 0.333 ft and 6 inches is 0.5 ft.
  5. Adjust the waste factor. Leave it at 10% for flat slabs on a clean gravel base, push to 15% for uneven subgrade or deep footings, drop to 5% only if your formwork is dialed.
  6. Enter your local ready-mix price per cubic yard so the cost estimate is realistic for your market.
  7. Read the primary result — cubic yards — to size your ready-mix order, and use the 60 lb and 80 lb bag counts to compare against bagged concrete from a home center.

The formula.

Yd³ = L × W × T × (1 + w) ⁄ 27

For slabs and footings the volume is rectangular: V_ft3 = length × width × thickness, with every dimension first converted to feet (1 m = 3.28084 ft, NIST SP 811). For columns the volume is cylindrical: V_ft3 = π × (d/2)² × h, where the diameter d is converted from inches to feet by dividing by 12 and the height h is converted to feet if you entered meters. The waste-adjusted volume is V_total = V_ft3 × (1 + wasteFactorPercent / 100). That total is then divided by 27 to get cubic yards (since 1 yd³ = 27 ft³) and by 35.3147 to get cubic meters. Bag counts use the Portland Cement Association published yields: a 60-pound bag of standard concrete mix yields 0.45 ft³ of cured concrete, and an 80-pound bag yields 0.60 ft³. The calculator divides total cubic feet by these yields and rounds up to the next whole bag, because you cannot buy a fractional bag. Total cost is simply cubic yards × your entered price per cubic yard, which is how ready-mix dispatchers price the load — pumping, short-load fees, fuel surcharges, and weekend premiums are separate line items not included here.

A worked example.

Example

You are pouring a 10 ft × 10 ft patio slab at 4 inches thick — a classic homeowner project. Raw volume is 10 × 10 × 0.333 = 33.33 cubic feet, which is 33.33 ÷ 27 = 1.23 cubic yards before waste. Apply the standard 10% waste cushion and the order becomes 36.67 ft³, or about 1.36 cubic yards. That is 1.04 cubic meters in metric. If you bagged it instead, you would need 36.67 ÷ 0.45 = 82 sixty-pound bags or 36.67 ÷ 0.60 = 62 eighty-pound bags — both numbers high enough that ready-mix is the obvious call. At $150 per cubic yard the material bill is roughly $204, before any short-load fee. A ready-mix truck will arrive with at least one yard on board (most suppliers have a one-yard minimum), so ordering 1.5 yards rounded up gives you a small safety buffer and avoids paying a short-load fee on a fraction.

unitft
waste Factor Percent10
diameter12
shapeslab
thickness0.333
price Per Yard150
length10
width10

Frequently asked questions.

When should I order ready-mix concrete versus bagged concrete?
Rule of thumb: above roughly half a cubic yard — about 30 of the 80-pound bags — order ready-mix. A delivered truck gives you a single continuous pour, consistent mix design, and saves hours of mixing. Below half a yard, bags win because most ready-mix suppliers charge a short-load fee of $50–$150 when you order less than a full yard, on top of a one-yard minimum. For a small fence-post footing or a single column, bags are almost always cheaper.
Should I use 3,000 PSI or 4,000 PSI concrete?
3,000 PSI is the standard residential mix for interior slabs, sidewalks, sheds, and patios that will not see freeze-thaw cycling. 4,000 PSI — with air entrainment — is what ACI 318 and most building codes recommend for driveways, exterior slabs in cold climates, and any structural footing. The price difference at the ready-mix plant is usually only $5–$10 per cubic yard, so for any pour that matters, ordering 4,000 PSI is cheap insurance against early surface scaling and freeze-thaw cracking.
Why is the standard waste factor 10 percent?
Ten percent is the field number that working concrete finishers and ready-mix dispatchers use because it covers the four real losses on every pour: over-excavation of the subgrade (gravel base settles), formwork that flexes outward slightly under the weight of fresh concrete, spillage from the chute and the wheelbarrow, and the small amount of concrete that hardens inside the truck drum on a hot day. ACI 301 and the NRMCA guidance both note that pouring exactly to calculated volume is virtually impossible, and most dispatchers will quietly round your order up anyway.
Do I need rebar or wire mesh in my slab?
For a 4-inch residential slab on grade, #3 or #4 rebar on 16- to 18-inch centers or 6×6 W2.9 welded wire mesh placed at the mid-depth is standard. The reinforcement does not stop concrete from cracking — it controls where cracks form and holds them tight. Driveways, garage slabs, and any slab carrying vehicle loads always get rebar; small patios and walkways sometimes use fiber-reinforced concrete instead. Footings always get rebar per ACI 318 — usually two #4 bars top and bottom in a continuous strip footing.
What is a slump test and do I need one for a home project?
A slump test (ASTM C143) measures concrete consistency by filling a 12-inch cone, removing the cone, and measuring how far the wet concrete sags. A 4- to 5-inch slump is normal for slab work, 3- to 4-inch for footings, and 6+ inch for pumped concrete. For homeowner projects you do not need to run a slump test yourself, but ask the ready-mix driver what slump the load left the plant at, and refuse any load with more than a 7-inch slump on slab work — that means extra water was added, which weakens the concrete.
How long until I can walk on or drive on new concrete?
Foot traffic: 24–48 hours after pour. Light vehicle traffic: 7 days. Full design strength (and full vehicle loading): 28 days, which is the standard curing window cylinders are tested at per ASTM C39. Concrete keeps gaining strength for months, but the 28-day number is what mix designs are rated to. Cover the slab with plastic sheeting or wet burlap for the first 7 days — keeping the surface damp roughly doubles the 28-day strength compared to letting it dry out.
How often do I need expansion or control joints in a slab?
Control joints (saw-cut or tooled) should be spaced at roughly 2 to 3 times the slab thickness in feet — so a 4-inch slab gets joints every 8 to 10 feet, and a 6-inch slab every 12 to 15 feet. Joints should be cut to 1/4 the slab depth, within 6 to 18 hours of the pour. Expansion joints (with compressible filler) separate the slab from fixed structures like the house foundation or a column footing, and prevent the slab from cracking those structures as it expands. ACI 360 has the full residential slab joint guidance.
Why does my calculation give a fractional yard but ready-mix is sold in whole and half yards?
Ready-mix suppliers will deliver in quarter-yard increments above the one-yard minimum, but they price in whole yards and charge a short-load fee when you order less than a full truck (typically 10 yards). Round your calculated number up to the nearest quarter yard. If the result is just under a yard — say, 0.9 yd³ — round up to a full yard rather than pay both the under-minimum fee and the short-load fee. Any small excess can be poured into a sacrificial mold (a stepping stone, a parking curb) instead of being wasted.
Does the calculator account for rebar displacement?
No, and you do not need it to. Steel reinforcement displaces less than 1% of the volume in a typical slab or footing, which is well inside the 10% waste cushion. Only on heavily reinforced structural elements — drilled shafts, mat foundations — does rebar displacement get added to the calculation, and that math is handled by the structural engineer on the project, not a homeowner volume estimator.

In this category

Embed

Quanta Pro

Paid features are coming later.

  • All 313 calculators remain free
  • No billing is enabled
Coming soon