Audited ·Last updated 31 Jul 2026·3 citations·Tier 2·0 uses

Transformer Sizing Calculator — Required kVA and the Next Standard Rating

Size a transformer from amps, kW or kVA, single or three phase. Adds your growth allowance and lands on a standard ANSI rating that is actually made.

Transformer Sizing Calculator

Describe the load as
Phase
The current the load draws at the secondary voltage. Used only when you describe the load in amps.
A
Used only in kilowatt mode, where it is divided by the power factor to get kVA. A nameplate that says kW is telling you real power, not the transformer's rating.
kW
Used only in kVA mode, where the figure is taken as given.
kVA
Used only in kilowatt mode. Motors typically run 0.8 to 0.9; resistive heating is 1.0. It must be greater than 0 and no more than 1.
Line-to-line for a three-phase system — 208 V or 480 V, not 120 V or 277 V. It sets both the load kVA in amps mode and the secondary full-load current.
V
Line-to-line on the supply side. It does not change the kVA needed — only the primary current, which is what the feeder and its protection have to carry.
V
Headroom added on top of the load before a rating is chosen. This is your design choice — it is not a code requirement and no figure on this page comes from the NEC. Enter 0 for none.
%
Recommended standard rating
75
The smallest self-cooled size in ANSI C57.12.50-1981 Table 1 that covers the requirement. Standard sizes are widely spaced, so the recommendation often has a lot more capacity than the requirement — that is the ladder, not the arithmetic.
Load apparent power
36.0267 kVA
Required with spare capacity
45.0333 kVA
Load as a share of nameplate
48.04
Spare above the requirement
66.54
Secondary full-load current
208.1792 A
Primary full-load current
90.211 A
Reading the result
A 36.03 kVA three-phase load plus 25 % spare capacity needs 45.03 kVA, so the smallest standard size that covers it is 75 kVA. At that rating the load sits at 48.04 % of nameplate, drawing 100 A of the 208.18 A the secondary can carry. That leaves 66.54 % above the requirement, because standard sizes are widely spaced: the ladder jumps in steps of 50 % or more at this end, so a load a fraction over a size costs a whole size. The 25 % allowance is your design choice, not a code requirement, and nothing on this page comes from the NEC. Scope: the sizes come from ANSI C57.12.50-1981 Table 1, which covers ventilated dry-type distribution transformers only, with high voltage 601–34 500 V and low voltage 120–600 V. That edition is old and manufacturers list ratings it does not, so confirm the size against a current catalogue. Installation and overcurrent protection are governed by NFPA 70 (National Electrical Code) Article 450 and by local amendments, the adopted edition varies by jurisdiction, and this page sizes neither protection nor conductors. A licensed electrician or engineer must sign off before anything is installed.

Background.

Sizing a transformer is two separate problems, and most calculators only solve the first. The first is arithmetic: turn the load into apparent power, because a transformer is rated in kVA and not in kilowatts, and add whatever spare capacity the design calls for. The second is that you cannot order the answer. Transformers are built in a fixed ladder of sizes, and a requirement of 45.03 kVA does not buy you a 45.03 kVA transformer — it buys you a 75 kVA one, because 45 is a standard size and the next one up is 75.

This page does both. Describe the load in amps at the secondary voltage, in kilowatts with a power factor, or in kVA if you have already worked it out; pick single-phase or three-phase; add a growth allowance; and it returns the smallest standard rating that covers the requirement, along with the full-load current on both sides of that rating.

The sizes come from ANSI C57.12.50-1981, Table 1, 'Self-Cooled Kilovolt-Ampere Sizes'. Single-phase: 1, 3, 5, 7.5, 10, 15, 25, 37.5, 50, 75, 100, 167, 250, 333, 500. Three-phase: 15, 30, 45, 75, 112.5, 150, 225, 300, 500. Note how far apart the steps are at the top — from 45 to 75 is a 67 % jump — which is why the utilisation figure this page reports is often much lower than people expect, and why it is not evidence of over-sizing.

Two scope limits sit beside every result rather than in a footnote. The standard cited covers ventilated dry-type distribution transformers with high voltage 601–34 500 V and low voltage 120–600 V, and it stops at 500 kVA; anything larger is a different standard and this page refuses to answer rather than extrapolate a size that may not exist. And the 1981 edition is old — later editions and individual manufacturers list ratings it does not — so confirm the size against a current catalogue before ordering.

Finally, the part that matters most. Choosing a kVA number is not designing an installation. In the United States, transformer installation and overcurrent protection are governed by NFPA 70, the National Electrical Code, Article 450; the adopted edition varies by jurisdiction and local amendments govern. **No figure on this page is taken from the NEC** — the growth allowance is your own design choice and is labelled as such — and this page sizes neither overcurrent protection nor conductors nor clearances. A licensed electrician or engineer must sign off before anything is installed.

What is transformer sizing calculator?

Transformer capacity is quoted in kilovolt-amps rather than kilowatts because the two limits inside a transformer are current, which heats the windings, and voltage, which stresses the insulation. Neither cares about the phase angle between voltage and current, so a transformer that can deliver 100 kVA delivers it whether the load is a resistive heater at unity power factor drawing 100 kW or a motor bank at 0.8 power factor drawing 80 kW. Converting a load to kVA therefore comes first: from amps it is V × I ÷ 1000 for single-phase and √3 × V × I ÷ 1000 for three-phase, using the line-to-line voltage; from kilowatts it is kW ÷ power factor. Adding spare capacity comes second and is a judgement rather than a formula — how much a building's load is expected to grow, how much of the connected load runs at once, how much margin the owner wants to pay for. Landing on a rating comes third, and is not a judgement at all: the sizes exist or they do not. That is why this page separates the required figure from the recommended rating and reports both, along with how much headroom the gap between them actually gives you.

How to use this calculator.

  1. Choose how you know the load — amps, kilowatts with a power factor, or kVA — and whether the system is single- or three-phase.
  2. Enter the load. In amps mode it is measured at the secondary voltage; in kilowatt mode it is real power, so the power factor matters.
  3. Enter the secondary and primary voltages, line-to-line for three-phase. The primary voltage does not change the kVA, only the primary current.
  4. Enter the spare capacity you want. This is a design decision, not a code figure — enter 0 if you want the bare requirement.
  5. Read the recommended standard rating. Then read the required kVA beside it: if the two are far apart, that is the spacing of the standard ladder, not over-sizing.
  6. Check the two full-load currents. They are what the conductors and protection on each side have to be rated for — sizing those is a separate job this page does not do.
  7. Confirm the rating against a current manufacturer catalogue, and have a licensed professional review the installation.

The formula.

kVA₁φ = V·I ⁄ 1000 kVA₃φ = √3·V·I ⁄ 1000 kVA = kW ⁄ pf required = kVA × (1 + growth⁄100)

Start by converting the load into apparent power, because that is the only thing a transformer is rated in. Take the worked example: 100 A on a three-phase 208 V secondary. Three-phase apparent power is √3 × V × I, so 1.7320508 × 208 × 100 = 36026.66 VA, or 36.0266567974 kVA. Had this been single-phase, the √3 would simply not be there.

If the load is given in kilowatts instead, divide by the power factor: 36 kW at 0.8 power factor is 45 kVA, and it is the 45 that the transformer has to be able to deliver. Getting this backwards — sizing a transformer from kilowatts and ignoring the power factor — under-sizes it by exactly the power factor, which for a motor load is a 20 to 25 % error.

Now add the spare capacity. With 25 % the requirement is 36.0266567974 × 1.25 = 45.0333209968 kVA. And here is where the example earns its place: the three-phase ladder contains 45 kVA, and the requirement misses it by 0.033 kVA — under a tenth of a percent. There is no 45.05 kVA transformer, so the answer is 75 kVA, the next size up. A load 0.07 % over a standard size costs an entire size.

That is also why the utilisation figure comes out at 48.04 %: the load is not half of what the transformer can do because anyone over-specified it, but because the standard ladder has nothing between 45 and 75. The headroom figure, 66.54 %, says the same thing about the requirement rather than the load.

The full-load currents come from the chosen rating, not from the load: 75 kVA at 208 V three-phase is 75000 ÷ (1.7320508 × 208) = 208.18 A on the secondary, and 75000 ÷ (1.7320508 × 480) = 90.21 A on the 480 V primary. Their ratio is 480/208, the voltage ratio, exactly as an ideal transformer requires. Those are the numbers the conductors and overcurrent devices on each side have to be chosen against — and choosing them is a different calculation that this page does not perform.

Rounding happens once, at the return boundary, and the headroom band reads the unrounded value, so a requirement that is a hair over a standard size is treated as over it even when it displays as equal.

What this page refuses to do. Above 500 kVA the cited table has no entries, and rather than invent a size the calculator stops and says so: units of 501 kVA and larger are covered by a separate standard that this page does not implement. That refusal is deliberate. A size that does not exist is worse than no answer, because it looks like one.

A worked example.

Example

A three-phase panel drawing 100 A at 208 V, fed from a 480 V supply, with 25 % spare capacity wanted. Apparent power is √3 × 208 × 100 ÷ 1000 = 36.0266567974 kVA. Adding the allowance gives a requirement of 45.0333209968 kVA — which misses the 45 kVA standard size by 0.033 kVA, about seven hundredths of a percent. Since there is no transformer between 45 and 75 kVA in the three-phase ladder, the recommendation is 75 kVA. That leaves 66.5433468816 % headroom over the requirement and puts the connected load at 48.0355423966 % of nameplate; neither figure is evidence of over-sizing, they are the spacing of the standard ladder. At 75 kVA the secondary can carry 208.179183602 A and the primary 90.2109795609 A, and the ratio between those two currents is 480 ÷ 208, exactly the voltage ratio. Two things this result does not settle: the conductors and overcurrent protection on either side, which are a separate calculation governed by NFPA 70 Article 450 and by local amendments, and whether a 75 kVA ventilated dry-type unit is actually stocked in the configuration you need — confirm that against a current manufacturer catalogue, because the standard cited here is the 1981 edition.

growth Margin Percent25
load Kilowatts30
phasethree
load Input Modeamps
secondary Voltage208
load Kilovolt Amps36
load Current100
power Factor0.85
primary Voltage480

Frequently asked questions.

Why is a transformer rated in kVA and not kW?
Because the two things that limit a transformer — winding current and insulation voltage — are indifferent to the phase angle between them. A 100 kVA transformer delivers 100 kVA whether that is 100 kW into a resistive heater at unity power factor or 80 kW into a motor bank at 0.8. Rating it in kilowatts would mean the same piece of iron carried two different numbers depending on what was plugged into it. The practical consequence is on this page: if your load is given in kilowatts, divide by the power factor before sizing, or you will under-size by exactly that factor.
Where do the standard kVA sizes come from?
From ANSI C57.12.50-1981, Table 1, 'Self-Cooled Kilovolt-Ampere Sizes', which lists 1, 3, 5, 7.5, 10, 15, 25, 37.5, 50, 75, 100, 167, 250, 333 and 500 kVA for single-phase and 15, 30, 45, 75, 112.5, 150, 225, 300 and 500 kVA for three-phase. That standard covers ventilated dry-type distribution transformers with high voltage 601–34 500 V and low voltage 120–600 V, and it is a 1981 edition. Later editions and individual manufacturers list ratings it does not, and liquid-filled units follow a different standard. Treat the answer as a starting point and confirm it against a current catalogue.
Why did my 45.03 kVA requirement recommend a 75 kVA transformer?
Because 45.03 kVA is not a size anybody makes. The three-phase ladder goes 45, then 75, so a requirement less than a tenth of a percent over 45 has to take the 75. This is the single most useful thing this calculator tells you, and it is worth reacting to: if your growth allowance was a round guess rather than a firm number, shaving it from 25 % to 24 % would bring the requirement under 45 and save an entire size. Look at the required figure, not just the recommendation, before you accept the jump.
How much spare capacity should I add?
That is a design judgement and this page will not pretend otherwise — the allowance is an input, its default of 25 % is a convention rather than a rule, and no figure on this page is taken from the NEC. What goes into the decision: how much of the connected load actually runs at once, how much the load is expected to grow over the transformer's life, whether the load includes motors with high starting currents, and how much a jump to the next standard size costs. Because the ladder is coarse, the allowance often does not change the answer at all — which is worth checking before agonising over it.
Does this size the breaker and the cables too?
No, and that is deliberate. Overcurrent protection for a transformer and its conductors is governed by NFPA 70, the National Electrical Code, Article 450, together with the articles covering feeders and conductor ampacity — and the adopted edition and local amendments vary by jurisdiction. Those rules involve percentages of full-load current that depend on the transformer's impedance, its location and whether protection is provided on one side or both. This page gives you the full-load current on each side, which is the input to that work, and stops there. A licensed electrician or engineer must do the rest.
Why does the calculator refuse loads above 500 kVA?
Because the table it works from stops there. ANSI C57.12.50-1981 covers 1 to 500 kVA single-phase and 15 to 500 kVA three-phase; units of 501 kVA and larger are covered by a separate standard which this page does not implement. Rather than extrapolate the pattern and offer a size that may not exist, the calculator stops and says so. A confidently wrong rating is worse than no rating, because it looks like an answer. Anything in that range should be sized with an engineer in any case.

References& sources.

  1. [1]ANSI C57.12.50-1981, 'American National Standard Requirements for Ventilated Dry-Type Distribution Transformers, 1 to 500 kVA, Single-Phase, and 15 to 500 kVA, Three-Phase, with High-Voltage 601 to 34 500 Volts, Low-Voltage 120 to 600 Volts' (Secretariat: IEEE; approved by ANSI 15 August 1980; published 1981). Sole source of the rating ladder implemented. §4.1.2: 'Self-cooled (AA) kilovolt-ampere sizes shall be as shown in Table 1.' Table 1 'Self-Cooled Kilovolt-Ampere Sizes' lists, single-phase: 1, 3, 5, 7.5, 10, 15, 25, 37.5, 50, 75, 100, 167, 250, 333, 500; three-phase: 15, 30, 45, 75, 112.5, 150, 225, 300, 500. §4.1.1 adds that the ratings 'are continuous and based on not exceeding a 150°C average winding temperature rise, as measured by resistance (220°C limiting temperature)'. The foreword notes that units of 501 kVA and larger are covered by ANSI C57.12.51-1981, which is why this page refuses above 500 kVA. PDF; text extracted locally. Retrieved 2026-07-29.
  2. [2]OpenStax (Rice University), University Physics Volume 2, §15.6 'Transformers'. Source of the power relation underlying the full-load current outputs: for an ideal transformer 'i_P(t)v_P(t) = i_S(t)v_S(t)', so the primary and secondary full-load currents at a given rating stand in the inverse ratio of the voltages — which is what this page's two current outputs satisfy. Also the source of the real-world caveat that 'a good transformer can have losses as low as 1% of the transmitted power', meaning the primary side draws slightly more than the secondary delivers. Retrieved 2026-07-29.
  3. [3]ANSI C57.12.51-1981, 'American National Standard Requirements for Ventilated Dry-Type Power Transformers, 501 kVA and Larger, Three-Phase, with High-Voltage 601 to 34 500 Volts, Low-Voltage 208Y/120 to 4160 Volts'. Named in the foreword of C57.12.50-1981 as the standard covering units above the range this page implements. Cited to identify precisely what is out of scope: the calculator refuses requirements above 500 kVA and points the reader here rather than extrapolating a rating. Bibliographic reference only — the document itself was not opened, and no figure on this page comes from it. Retrieved 2026-07-29 via the C57.12.50-1981 foreword.

In this category

Embed

Quanta Pro

Paid features are coming later.

  • All 977 calculators remain free
  • No billing is enabled
Coming soon