Electrical Service Load Calculator
Turn a connected or NEC-calculated load into design volt-amperes and amps using a demand factor, margin and voltage, then compare with your service rating.
Electrical Service Load Calculator
Background.
A 200-amp panel does not mean a house can run 200 amps of appliances at once, and a 100-amp panel is not automatically too small for a heat pump. What decides it is the calculated load: everything connected, discounted for the fact that it never all runs together, converted to amperes and set against the rating of the service. That question comes up before almost every big electrical addition, whether an EV charger, a heat pump, an induction range or a hot tub, and many permit offices ask to see the calculation.
The calculator handles the last two steps of that job. You give it a load in volt-amperes, either a raw total of nameplate ratings or a figure already worked out under the National Electrical Code, together with a demand factor and a design margin. It multiplies the load by the factor, adds the margin on top and divides by the system voltage, so the second result reads directly in amperes for a 240-volt single-phase service. With the defaults, 10,000 VA at 80% demand with a 25% margin comes back as 10,000 VA, or 41.6667 A.
The code calculation itself is not built in. Article 220 of the 2023 NEC, the edition cited here, never applies one percentage to a whole house: lighting, cooking, laundry, heating and cooling each get their own treatment, and even the shorter optional method for dwellings takes the first 10 kVA of general load at 100% and the rest at 40%. A single factor can only reproduce those results after the tiers have been worked by hand, so the most dependable way to use this tool is to enter a load that has already been calculated, set the demand factor to 100% and use the margin for whatever headroom you want.
An adequate service also takes more than an ampere rating. Conductor size, the meter base, the utility's transformer and the available fault current all have to agree, and the code edition your jurisdiction has adopted changes the arithmetic itself. A licensed electrician and the local inspector decide whether a service is adequate. The figure here tells you roughly where you stand before that conversation.
What is electrical service load calculator?
Service load is the demand an electrical service must be able to carry, stated in volt-amperes and then in amperes at the service voltage. Connected load is the total of everything that could draw power: every appliance nameplate and every lighting and receptacle circuit. Calculated load, also called demand load, is the smaller figure the code allows the service to be sized for, because a water heater, a dryer, an oven and an air conditioner seldom all peak in the same quarter-hour. The ratio of the two is the demand factor. At 240 volts a 100 A service carries 24,000 VA and a 200 A service 48,000 VA. Whatever the arithmetic says, the NEC does not allow a one-family dwelling a service disconnect rated below 100 A. Design load, in this calculator's terms, is the demand load with a margin added for loads you expect to install later.
How to use this calculator.
- In Connected or calculated load, enter the load in volt-amperes; watts are close enough for heaters, ovens and lighting. If you have an electrician's load sheet or your own Article 220 calculation, enter its total. Otherwise add up the nameplate ratings of the fixed appliances (on the label inside the door, on the back panel or in the manual) and the floor-area allowance for lighting and receptacles. A sum of breaker ratings is not a load.
- In Applicable demand factor, enter 100% when the load is already a calculated load, because the code's discounts are already inside it. Enter something lower only for a raw nameplate total, and choose it knowingly: worked on general loads alone, the optional method's tiers come to an effective 70% at 20,000 VA and 52% at 50,000 VA.
- In Design margin, enter the headroom you want on top. A margin of 0% shows the bare calculated load against the service rating; the default 25% leaves space for something like a future heat pump or charger. For an existing service judged from measured peak demand, 25% is the code's own requirement (see the worked example).
- In System voltage or design divisor, enter 240 for an ordinary North American single-phase house service. For a balanced three-phase service enter √3 times the line voltage, 360.27 for 208 V or 831.38 for 480 V. If you entered the load in kVA, enter the voltage in kilovolts (0.24) and the result is still in amperes.
- Read Load per design divisor as the current the service must carry and compare it with the rating of the main breaker. A result close to the rating is a reason to get a full code calculation done, not a verdict either way.
The formula.
Demand-adjusted load = L × d, and design load = L × d × (1 + m), where L is the connected or calculated load, d the demand factor and m the design margin, both entered as percentages and used as fractions. The last output divides by V: I = L × d × (1 + m) ÷ V. For single-phase power, volt-amperes divided by volts gives amperes, so with V = 240 the result is the current on each ungrounded conductor of a 120/240 V service. For a balanced three-phase load the line current is VA ÷ (√3 × line voltage), which is why the divisor field accepts 360.27 for 208 V or 831.38 for 480 V.
Because d and m multiply, they can cancel. The defaults, 80% and 25%, multiply to exactly 1, and the design load comes back equal to the connected load. The pairing is familiar for a reason: 80% and 125% are one rule seen from two sides. The NEC sizes conductors and overcurrent devices for continuous loads, those running three hours or more, at 125% of the load, which is the same as loading a standard breaker to no more than 80% of its rating. Entering 80% and 25% together therefore says nothing about diversity at all.
The single factor is the model's main simplification. Code demand factors depend on the kind of load. In a dwelling, general lighting is taken at 100% for the first 3,000 VA, 35% from there to 120,000 VA and 25% beyond; four or more fastened-in-place appliances may be taken at 75%; a dryer counts as at least 5,000 W; one range rated up to 12 kW counts as 8 kW; heating and cooling are noncoincident, so only the larger is counted; and 25% of the largest motor is added. Because the tiers bite harder as a house grows, no fixed percentage fits every house: the optional method's 10 kVA at 100% and 40% after that works out to 70% of 20,000 VA but 52% of 50,000 VA.
Also outside the model: power factor (enter VA rather than watts where motors are a large share), the neutral load, voltage drop, and the 125% treatment of individual continuous loads such as EV chargers.
A worked example.
Take the defaults: 10,000 VA of connected load, an 80% demand factor, a 25% margin and 240 V. The demand-adjusted load is 10,000 × 0.80 = 8,000 VA. Adding the margin gives 8,000 × 1.25 = 10,000 VA of design load, back where it started because 0.80 × 1.25 = 1. Dividing by the voltage, 10,000 ÷ 240 = 41.6667 A, which is 20.8333% of a 200 A service and 41.6667% of a 100 A one. A more useful run starts from measured demand. Section 220.87 of the 2023 NEC lets an existing service be judged from its actual peak: the highest demand in a year of utility records, or failing that a recording of at least 30 days in 15-minute averages, taken at 125%, with the new load added in full. Suppose the utility's records show a 9,600 W peak and the owner wants a 32 A EV charger. Entering 9,600 with a 100% demand factor and a 25% margin returns 12,000 VA and exactly 50 A. The charger adds 32 × 240 = 7,680 VA, which is 32 A, so the total is 19,680 VA, or 82 A, within the rating of a 100 A service. Measured demand records what the house actually drew, including the diversity that the tiered rules can only approximate.
Frequently asked questions.
How do I work out a calculated load with the NEC optional method?
Is a 100-amp service big enough for my house?
Can I use my utility's demand data instead of adding up appliances?
Why can't I just add up the breakers in my panel?
Will an EV charger fit on my existing service?
What demand factor should I type in?
Is the 25% default margin the same as the NEC's 125% continuous-load rule?
What should I enter for a 208-volt or three-phase building?
Which edition of the electrical code applies to my project?
Do watts and volt-amperes mean the same thing in a load calculation?
References& sources.
- [1]NFPA 70, National Electrical Code 2023; load calculations, feeders and continuous loads. Retrieved 2026-08-07.
- [2]International Code Council. 2024 International Residential Code (IRC). Retrieved 2026-08-07.
- [3]U.S. Occupational Safety and Health Administration. Electrical — standards and hazards. Retrieved 2026-08-07.
- [4]U.S. Department of Energy. Energy Saver. Retrieved 2026-08-07.
- [5]U.S. Energy Information Administration. Electric power monthly — average retail price of electricity. Retrieved 2026-08-07.
How this page was produced
- Published by
- Quanta Calculator
- Overseen by
- Daniel, Quanta Calculator Researcher
- Primary sources
- 5 cited below
- Method
- design load = connected load × demand factor × (1 + design margin)
- Published
- Last verified
Built with AI assistance and verified by automated tests against the cited sources — every worked example on this page is computed by the same code that runs the calculator. How we build and check calculators.
In this category
Embed
Quanta Pro
Paid features are coming later.
- All 1560 calculators remain free
- No billing is enabled