Audited 05 Aug 2026·Last updated 28 Oct 2026·5 citations·Tier 1·0 uses

Electrical Service Load Calculator

Turn a connected or NEC-calculated load into design volt-amperes and amps using a demand factor, margin and voltage, then compare with your service rating.

Electrical Service Load Calculator

%
%
Design load
10,000
The demand-adjusted load with your design margin added, in volt-amperes (or whatever unit you entered the load in).
Load per design divisor
41.6667
Demand-adjusted load
8,000

Background.

A 200-amp panel does not mean a house can run 200 amps of appliances at once, and a 100-amp panel is not automatically too small for a heat pump. What decides it is the calculated load: everything connected, discounted for the fact that it never all runs together, converted to amperes and set against the rating of the service. That question comes up before almost every big electrical addition, whether an EV charger, a heat pump, an induction range or a hot tub, and many permit offices ask to see the calculation.

The calculator handles the last two steps of that job. You give it a load in volt-amperes, either a raw total of nameplate ratings or a figure already worked out under the National Electrical Code, together with a demand factor and a design margin. It multiplies the load by the factor, adds the margin on top and divides by the system voltage, so the second result reads directly in amperes for a 240-volt single-phase service. With the defaults, 10,000 VA at 80% demand with a 25% margin comes back as 10,000 VA, or 41.6667 A.

The code calculation itself is not built in. Article 220 of the 2023 NEC, the edition cited here, never applies one percentage to a whole house: lighting, cooking, laundry, heating and cooling each get their own treatment, and even the shorter optional method for dwellings takes the first 10 kVA of general load at 100% and the rest at 40%. A single factor can only reproduce those results after the tiers have been worked by hand, so the most dependable way to use this tool is to enter a load that has already been calculated, set the demand factor to 100% and use the margin for whatever headroom you want.

An adequate service also takes more than an ampere rating. Conductor size, the meter base, the utility's transformer and the available fault current all have to agree, and the code edition your jurisdiction has adopted changes the arithmetic itself. A licensed electrician and the local inspector decide whether a service is adequate. The figure here tells you roughly where you stand before that conversation.

What is electrical service load calculator?

Service load is the demand an electrical service must be able to carry, stated in volt-amperes and then in amperes at the service voltage. Connected load is the total of everything that could draw power: every appliance nameplate and every lighting and receptacle circuit. Calculated load, also called demand load, is the smaller figure the code allows the service to be sized for, because a water heater, a dryer, an oven and an air conditioner seldom all peak in the same quarter-hour. The ratio of the two is the demand factor. At 240 volts a 100 A service carries 24,000 VA and a 200 A service 48,000 VA. Whatever the arithmetic says, the NEC does not allow a one-family dwelling a service disconnect rated below 100 A. Design load, in this calculator's terms, is the demand load with a margin added for loads you expect to install later.

How to use this calculator.

  1. In Connected or calculated load, enter the load in volt-amperes; watts are close enough for heaters, ovens and lighting. If you have an electrician's load sheet or your own Article 220 calculation, enter its total. Otherwise add up the nameplate ratings of the fixed appliances (on the label inside the door, on the back panel or in the manual) and the floor-area allowance for lighting and receptacles. A sum of breaker ratings is not a load.
  2. In Applicable demand factor, enter 100% when the load is already a calculated load, because the code's discounts are already inside it. Enter something lower only for a raw nameplate total, and choose it knowingly: worked on general loads alone, the optional method's tiers come to an effective 70% at 20,000 VA and 52% at 50,000 VA.
  3. In Design margin, enter the headroom you want on top. A margin of 0% shows the bare calculated load against the service rating; the default 25% leaves space for something like a future heat pump or charger. For an existing service judged from measured peak demand, 25% is the code's own requirement (see the worked example).
  4. In System voltage or design divisor, enter 240 for an ordinary North American single-phase house service. For a balanced three-phase service enter √3 times the line voltage, 360.27 for 208 V or 831.38 for 480 V. If you entered the load in kVA, enter the voltage in kilovolts (0.24) and the result is still in amperes.
  5. Read Load per design divisor as the current the service must carry and compare it with the rating of the main breaker. A result close to the rating is a reason to get a full code calculation done, not a verdict either way.

The formula.

design load = connected load × demand factor × (1 + design margin)

Demand-adjusted load = L × d, and design load = L × d × (1 + m), where L is the connected or calculated load, d the demand factor and m the design margin, both entered as percentages and used as fractions. The last output divides by V: I = L × d × (1 + m) ÷ V. For single-phase power, volt-amperes divided by volts gives amperes, so with V = 240 the result is the current on each ungrounded conductor of a 120/240 V service. For a balanced three-phase load the line current is VA ÷ (√3 × line voltage), which is why the divisor field accepts 360.27 for 208 V or 831.38 for 480 V.

Because d and m multiply, they can cancel. The defaults, 80% and 25%, multiply to exactly 1, and the design load comes back equal to the connected load. The pairing is familiar for a reason: 80% and 125% are one rule seen from two sides. The NEC sizes conductors and overcurrent devices for continuous loads, those running three hours or more, at 125% of the load, which is the same as loading a standard breaker to no more than 80% of its rating. Entering 80% and 25% together therefore says nothing about diversity at all.

The single factor is the model's main simplification. Code demand factors depend on the kind of load. In a dwelling, general lighting is taken at 100% for the first 3,000 VA, 35% from there to 120,000 VA and 25% beyond; four or more fastened-in-place appliances may be taken at 75%; a dryer counts as at least 5,000 W; one range rated up to 12 kW counts as 8 kW; heating and cooling are noncoincident, so only the larger is counted; and 25% of the largest motor is added. Because the tiers bite harder as a house grows, no fixed percentage fits every house: the optional method's 10 kVA at 100% and 40% after that works out to 70% of 20,000 VA but 52% of 50,000 VA.

Also outside the model: power factor (enter VA rather than watts where motors are a large share), the neutral load, voltage drop, and the 125% treatment of individual continuous loads such as EV chargers.

A worked example.

Example

Take the defaults: 10,000 VA of connected load, an 80% demand factor, a 25% margin and 240 V. The demand-adjusted load is 10,000 × 0.80 = 8,000 VA. Adding the margin gives 8,000 × 1.25 = 10,000 VA of design load, back where it started because 0.80 × 1.25 = 1. Dividing by the voltage, 10,000 ÷ 240 = 41.6667 A, which is 20.8333% of a 200 A service and 41.6667% of a 100 A one. A more useful run starts from measured demand. Section 220.87 of the 2023 NEC lets an existing service be judged from its actual peak: the highest demand in a year of utility records, or failing that a recording of at least 30 days in 15-minute averages, taken at 125%, with the new load added in full. Suppose the utility's records show a 9,600 W peak and the owner wants a 32 A EV charger. Entering 9,600 with a 100% demand factor and a 25% margin returns 12,000 VA and exactly 50 A. The charger adds 32 × 240 = 7,680 VA, which is 32 A, so the total is 19,680 VA, or 82 A, within the rating of a 100 A service. Measured demand records what the house actually drew, including the diversity that the tiered rules can only approximate.

connected Load10,000
demand Factor Percent80
design Margin Percent25
system Voltage240

Frequently asked questions.

How do I work out a calculated load with the NEC optional method?
The 2023 NEC's optional method (220.82) covers a dwelling on a 120/240 V or 208Y/120 V three-wire service or feeder of 100 A or more. Add 3 VA per square foot, 1,500 VA for each small-appliance and laundry circuit, and the nameplate ratings of fastened-in-place appliances, ranges, dryers, water heaters and permanent motors. The first 10 kVA counts in full, the rest at 40%, and then the largest heating or cooling selection is added, central air at 100%. A 2,000 sq ft house with two kitchen circuits, a laundry circuit, a 12 kW range, a 5,000 W dryer, a 4,500 W water heater, 1,200 VA of dishwasher and furnace blower and 5,000 VA of air conditioning has 33,200 VA of general load. That becomes 10,000 + 0.4 × 23,200 = 19,280 VA, plus 5,000 for cooling: 24,280 VA. Entered at 100% demand with no margin, it gives 101.1667 A.
Is a 100-amp service big enough for my house?
Compare Load per design divisor with 100 A, using a calculated load rather than a nameplate total. A 100 A service at 240 V carries 24,000 VA. The all-electric house in the previous answer calculates to 101.1667 A, just over it. With a gas range, dryer and water heater instead, leaving out their small electrical loads, the same method gives 15,680 VA, or 65.3333 A. Either way, 100 A is also the smallest service the NEC permits for a one-family dwelling.
Can I use my utility's demand data instead of adding up appliances?
For an existing service, yes, if the data meet the conditions of 220.87: a full year of maximum-demand readings, or else a recording of at least 30 days in 15-minute averages on the most heavily loaded phase, taken while the building is occupied and including the larger of the heating or cooling load. Many utilities can supply interval data from smart meters. The peak is taken at 125%, which the Design margin field reproduces at 25%, and the new load is added in full.
Why can't I just add up the breakers in my panel?
Breaker ratings say what each circuit is allowed to carry, not what it actually carries. A panel of 15 A and 20 A circuits commonly adds up to several times the main breaker's rating with nothing wrong, because general-purpose circuits run far below their ratings almost all the time. That gap is exactly the diversity the code's demand factors describe. Start from the nameplate ratings of the equipment, or from measured demand.
Will an EV charger fit on my existing service?
Work it out as an addition. Under the 2023 NEC an EV charger counts in the standard calculation as 7,200 VA or its nameplate rating, whichever is larger, and charging is a continuous load, so the charger's own circuit is sized at 125%: a 32 A charger needs a 40 A circuit. Add its VA to the existing calculated or measured load. If the total comes out short, the 2023 edition also lets an energy management system that caps the service current be counted at its setpoint, an alternative to upgrading the service.
What demand factor should I type in?
If the load came from a code calculation, 100%: its discounts are already inside it, and a second factor would count them twice. For a raw nameplate total there is no single right number, because the code's discounts are tiered. On general loads alone the optional method works out to 70% at 20,000 VA, 58.0723% at 33,200 VA and 52% at 50,000 VA, and heating or cooling is then added at up to 100%. A spread that wide is why a guessed factor is good only for a first look.
Is the 25% default margin the same as the NEC's 125% continuous-load rule?
No, although the numbers match. The 125% rule applies to continuous loads, those running three hours or more, when sizing conductors and overcurrent devices, and only to those loads, not to a whole service. The code also takes measured peak demand at 125% when judging an existing service. Beyond those cases, headroom for future loads is a design choice. And since 0.80 × 1.25 = 1, the default 80% factor with a 25% margin returns the connected load unchanged.
What should I enter for a 208-volt or three-phase building?
It depends on the wiring. An apartment fed from two legs of a 208Y/120 V system is single-phase at 208 V: enter 208, and 10,000 VA becomes 48.0769 A, about 15% more current than at 240 V. For a balanced three-phase service enter √3 times the line voltage, 360.27 for 208 V or 831.38 for 480 V, and the same 10,000 VA becomes 27.757 A or 12.0282 A per phase. Unbalanced loads need a phase-by-phase calculation.
Which edition of the electrical code applies to my project?
The one your state or city has adopted, which can trail the newest edition by a cycle or two, along with any local amendments. The calculator cites the 2023 NEC. The 2026 edition moved load calculations from Article 220 to a new Article 120 and lowered the dwelling general-lighting load from 3 to 2 VA per square foot, cutting the floor-area allowance by a third. Some jurisdictions enforce the International Residential Code's electrical chapters for one- and two-family houses; those chapters are drawn from the NEC.
Do watts and volt-amperes mean the same thing in a load calculation?
For heaters, ovens, water heaters and incandescent lighting they are effectively equal. Motor loads draw current partly out of step with the voltage, so their volt-amperes exceed their watts by the inverse of the power factor: an air conditioner at a 0.9 power factor draws about 11% more VA than watts. Conductors carry current, so load calculations are done in VA. When a nameplate gives amps and volts, multiply them for VA rather than using a watt figure.

How this page was produced

Published by
Quanta Calculator
Primary sources
5 cited below
Method
design load = connected load × demand factor × (1 + design margin)
Published
Last verified

Built with AI assistance and verified by automated tests against the cited sources — every worked example on this page is computed by the same code that runs the calculator. How we build and check calculators.

In this category

Embed

Quanta Pro

Paid features are coming later.

  • All 1560 calculators remain free
  • No billing is enabled
Coming soon